A new logistics building will be constructed on the site. It will have a modular hall area of around 13,700 m². The new building will also have approx. 1,300 m² of mezzanine space and approx. 920 m² of office and social space. The rental space should be ready for occupancy in the 4th quarter of 2026.

The project is being realised as part of a joint venture with Taurus Investment Holdings.

Q4 2026
PROJECT COMPLETION
28.000
Property area
15.000
Total rental space

Key facts

  • Location: Neumünster industrial park
  • Land area: approx. 28,000 m²
  • Hall area: approx. 13,700 m²
  • Hall area divisibility: up to 2 units
  • Storage mezzanine: approx. 1,300 m²
  • Office and social area: approx. 920 m²
  • Ready for occupancy: planned
    for the fourth quarter of 2026
  • Road connection: B205/A7
  • Lighting: LED
  • Floor load capacity: 5 t/m²
  • Hall height: 10 m UKB
  • Loading: 18 delivery gates,
    3 of which are at ground level

ESG measures

  • Aiming for at least DGNB Gold certification
  • Development according to EU taxonomy requirements
  • Air-to-water heat pump with natural coolant
  • Installation of smart meters
  • Electric charging infrastructure
  • Photovoltaic system
  • Material pass
  • CRREM path calculation
  • Insect-friendly lighting
  • Biodiversity concept
  • Sustainability manual
  • Holistic sustainability concept can be fully customised to the needs of the tenants

CONSTRUCTION PROGRESS IN PICTURES

  • IMG_0812.jpg

    Interim status of the demolition work

    January 2025

  • DSC_4705a.jpg

    Old stock before the start of construction work

    January 2022

  • IMG_8566.JPG

    Completion of the demolition work

    April 2025

Jonas_baumeisterneu.png